DEVELOPMENT AT BATH STREET

A site visit earlier this week showcased the exciting development that’s been happening at Bath Street!

The first-floor slab of the hotel is officially complete, and the lightweight steel frame is progressing quickly as the 2nd floor is almost finished. The bathroom pods have been craned and positioned also, bringing the structure together.

Whilst demolition works continue on Rue de Funchal, the tower crane has been erected at the main residential block and the foundations of Blocks A and B are progressing quickly.

The Bath Street mixed-use development will ultimately provide a new, vibrant urban quarter for Islanders in the heart of the capital, and is due for first phase completion in November 2021.