PROGRESS FOR SAMARES

Phase Two construction is in full swing at Samares Nursery – this follows the completion of Phase One in November last year.

The second phase, Clos du Foyer, comprises first-time buyer units and a mix of one, two, and three bedroom rental accommodation, along with integrated recreational and green spaces.

Two ponds have also been introduced to the site for migrating birds and amphibians as part of the ecological mitigation works undertaken by GR Langlois Ltd in conjunction with Nurture Ecology.

Clos du Foyer construction is due for completion in spring.